Tag: substation project

Planned Power Outage in Loretto-Hilton Center July 17

Planned Power Outage in Loretto-Hilton Center July 17

| July 10, 2015 | 0 Comments

On Friday, July 17, starting at 7 a.m. and lasting until Saturday at 5 a.m., the contractor on the electrical substation project will replace outdated electrical switchgear in the Loretto-Hilton Center. The building will not be accessible to faculty, staff or students. To prepare for the work, occupants of the Loretto Hilton Center need to […]

Continue Reading

Planned Power Outage in University Center July 11

Planned Power Outage in University Center July 11

| July 6, 2015 | 0 Comments

On Saturday, July 11, the contractor will be preparing the transformer at the University Center for the changeover to the electrical customer substation. The building will not be accessible to faculty, staff, or students. How Staff in University Center Should Prepare To prepare for the work, the occupants of the University Center need to turn […]

Continue Reading

Impact on Thompson Music Building, Visual Arts Studio from Substation Project June 11-15

Impact on Thompson Music Building, Visual Arts Studio from Substation Project June 11-15

| June 8, 2015 | 0 Comments

Attention: Users of the Thompson Music Building, the Visual Arts Studio and Lot K, please note the impact of upcoming work from Phase 2 of the Electrical Customer Substation project: Visual Arts Studio On Friday, June, 12, 2015, starting at 7 a.m. and lasting until 4 p.m., the contractor will be replacing the outdated electrical […]

Continue Reading

Electrical Substation Phase 2: Transformer Work, June 8-12

Electrical Substation Phase 2: Transformer Work, June 8-12

| June 8, 2015 | 0 Comments

Work continues on Phase 2 of the Electrical Customer Substation project. Please see below for local impact of transformer work conducted the week of June 8-12. East and West Hall: On Monday June 8, 2015, the contractor will begin excavation work to tie the new conduits into the transformer for future electrical tie-ins at East […]

Continue Reading

Electrical Customer Substation Phase 2 Scheduled Work, Impact May 18-July 24

Electrical Customer Substation Phase 2 Scheduled Work, Impact May 18-July 24

| May 18, 2015 | 0 Comments

Work continues on Phase 2 of the Electrical Customer Substation project. Please see below for local impact of work conducted during the next few weeks. Electrical Wire Pulls On Monday, May 18, the contractor, Kozney-Wagner, will begin the preparation work for the pull of electrical wire through the underground ductbank and directionally bored conduits from […]

Continue Reading

Electrical Substation Phase 2 Work May 11-13

Electrical Substation Phase 2 Work May 11-13

| May 8, 2015 | 0 Comments

On Monday May 11, the contractor for the electrical customer substation project will begin the preparation work for the pull of electrical cables through the underground ductbank and directionally bored conduits from manhole # 2 in front of the Garden Avenue Parking Garage to manhole #6 south of the Pearson House and north of the […]

Continue Reading

Electrical Customer Substation Phase 2: Minor parking, pedestrian impact April 27-30

Electrical Customer Substation Phase 2: Minor parking, pedestrian impact April 27-30

| April 23, 2015 | 0 Comments

On Monday, April 27, the contractor Kozeny-Wagner will begin pulling electrical cables through the underground ductbank and directionally bored conduits from the new Electrical Customer Substation’s location along the south side of Garden Avenue, to east side of the East Academic Building, and to Manhole #6 south of the Pearson House. The contractor will block […]

Continue Reading

Electrical Customer Substation Phase 2: Work, impact April 13-17

Electrical Customer Substation Phase 2: Work, impact April 13-17

| April 10, 2015 | 0 Comments

Work continues for construction of the new electrical customer substation on the Webster Groves campus, which is an important step for constructing the new Interdisciplinary Science Building. The following Phase 2 updates outline the local impact of work scheduled for April 13-17. Monday, April 13, and Tuesday, April 14: The contractor for the electrical customer […]

Continue Reading

Electrical Customer Substation Phase 2 work March 27-April 2, some impact on Hazel and Garden

Electrical Customer Substation Phase 2 work March 27-April 2, some impact on Hazel and Garden

| March 24, 2015 | 0 Comments

On Friday, March 27, and Monday, March 30, the contractor will begin pulling the electrical cables through the underground duct bank and directionally bored conduits from the new electrical customer substation’s location along the south side of Garden Avenue to Manhole #4 by the Club House for the Webster Village Apartments. During this phase, there […]

Continue Reading

Electrical Customer Substation: Phase 2 work along Garden, Hazel

Electrical Customer Substation: Phase 2 work along Garden, Hazel

| March 19, 2015 | 0 Comments

Beginning the morning of Thursday, March 19, Aschinger Electric will begin cleaning and pumping out the manholes along Garden Avenue, by the University Center, Visual Arts and along Hazel Avenue. They will have personnel assisting with traffic control on Hazel Avenue. The Department of Facilities Planning and Management will keep the local Webster community informed […]

Continue Reading