Webster Groves Campus Construction Update, Nov. 29 – Dec. 5

| November 30, 2010
South patio and north courtyard construction photos on left taken Sep. 28; photos on right taken Nov. 23.

From Dan Hitchell, associate vice president, Resource Planning & Budget:

South Patio and North Courtyard:

The South Patio doors and North Courtyard entryway will be open Dec. 1, 2010. The patio doors, new corridor and courtyard entryway are ready for use, however, the contractor is still waiting on glass doors and windows to complete the project. The glass is due from the supplier within the next two weeks. It will be necessary to close the patio and entryway for two days while the glass installation takes place.

Another part of this project is to replace the original windows in Marletto’s with new energy efficient windows over winter break. Please watch Webster Today for updates on the closing and the work in Marletto’s.

Academic Building:

The rain on Wednesday and Thursday, Nov. 24 and 25 has caused the work on the new parking lot adjacent to Garden Park Plaza to fall slightly behind schedule. The paving work on the parking lot should be completed next week. Work continues on the building foundation.